{"id":19752,"date":"2026-11-19T14:04:59","date_gmt":"2026-11-19T14:04:59","guid":{"rendered":"https:\/\/himalayanlive.in\/?p=19752"},"modified":"2026-11-19T14:05:18","modified_gmt":"2026-11-19T14:05:18","slug":"uttarakhand-gets-forest-clearance-for-three-hydropower-projects-after-decades","status":"publish","type":"post","link":"https:\/\/himalayanlive.in\/?p=19752","title":{"rendered":"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades"},"content":{"rendered":"<p>Dehradun: The way has been cleared for three long-pending hydropower projects in Uttarakhand, with a combined capacity of 204 MW. The projects, being developed by Uttarakhand Jal Vidyut Nigam Limited (UJVNL), are expected to generate 886.17 million units of electricity annually.<\/p>\n<p>The projects include the 12 MW Tankul, 120 MW Sirkari Bhyol-Rupsiyabagar and 72 MW Tyuni-Plasu. Tankul has received final forest clearance along with Public Investment Board approval, while the other two projects have received final forest clearance.<\/p>\n<p>The approvals mark a major breakthrough, as the Tyuni-Plasu project dates back to 1971-72, while Sirkari Bhyol-Rupsiyabagar was allotted to UJVNL in 2004. The forest clearance process for Tankul began in 2019.<\/p>\n<p>UJVNL Managing Director Ajay Kumar Singh said that preparations are underway to award civil construction works and begin construction. The projects are expected to strengthen the state&#8217;s power generation capacity, improve electricity supply in border areas, particularly Pithoragarh, and create local employment opportunities.<\/p>\n<p><strong>Himalayan Live Bureau\u00a0<\/strong><\/p>\n<!--CusAds0-->\n<div style=\"font-size: 0px; height: 0px; line-height: 0px; margin: 0; padding: 0; clear: both;\"><\/div>","protected":false},"excerpt":{"rendered":"<p>Dehradun: The way has been cleared for three long-pending hydropower projects in Uttarakhand, with a&#8230;<\/p>\n","protected":false},"author":2,"featured_media":19753,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[4],"tags":[],"class_list":["post-19752","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-uttarakhand"],"aioseo_notices":[],"aioseo_head":"\n\t\t<!-- All in One SEO 5.0.5.1 - aioseo.com -->\n\t<meta name=\"description\" content=\"Dehradun: The way has been cleared for three long-pending hydropower projects in Uttarakhand, with a combined capacity of 204 MW. The projects, being developed by Uttarakhand Jal Vidyut Nigam Limited (UJVNL), are expected to generate 886.17 million units of electricity annually. The projects include the 12 MW Tankul, 120 MW Sirkari Bhyol-Rupsiyabagar and 72 MW\" \/>\n\t<meta name=\"robots\" content=\"max-image-preview:large\" \/>\n\t<meta name=\"author\" content=\"admin\"\/>\n\t<link rel=\"canonical\" href=\"https:\/\/himalayanlive.in\/?p=19752\" \/>\n\t\t<meta name=\"generator\" content=\"All in One SEO (AIOSEO) 5.0.5.1\" \/>\n\t\t<meta property=\"og:locale\" content=\"en_US\" \/>\n\t\t<meta property=\"og:site_name\" content=\"Himalayan Live -\" \/>\n\t\t<meta property=\"og:type\" content=\"article\" \/>\n\t\t<meta property=\"og:title\" content=\"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades - Himalayan Live\" \/>\n\t\t<meta property=\"og:description\" content=\"Dehradun: The way has been cleared for three long-pending hydropower projects in Uttarakhand, with a combined capacity of 204 MW. The projects, being developed by Uttarakhand Jal Vidyut Nigam Limited (UJVNL), are expected to generate 886.17 million units of electricity annually. The projects include the 12 MW Tankul, 120 MW Sirkari Bhyol-Rupsiyabagar and 72 MW\" \/>\n\t\t<meta property=\"og:url\" content=\"https:\/\/himalayanlive.in\/?p=19752\" \/>\n\t\t<meta property=\"og:image\" content=\"https:\/\/himalayanlive.in\/wp-content\/uploads\/2026\/11\/1280px-NSRS_Srisailam_Dam.jpg\" \/>\n\t\t<meta property=\"og:image:secure_url\" content=\"https:\/\/himalayanlive.in\/wp-content\/uploads\/2026\/11\/1280px-NSRS_Srisailam_Dam.jpg\" \/>\n\t\t<meta property=\"og:image:width\" content=\"1280\" \/>\n\t\t<meta property=\"og:image:height\" content=\"960\" \/>\n\t\t<meta property=\"article:published_time\" content=\"2026-11-19T14:04:59+00:00\" \/>\n\t\t<meta property=\"article:modified_time\" content=\"2026-11-19T14:05:18+00:00\" \/>\n\t\t<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n\t\t<meta name=\"twitter:title\" content=\"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades - Himalayan Live\" \/>\n\t\t<meta name=\"twitter:description\" content=\"Dehradun: The way has been cleared for three long-pending hydropower projects in Uttarakhand, with a combined capacity of 204 MW. The projects, being developed by Uttarakhand Jal Vidyut Nigam Limited (UJVNL), are expected to generate 886.17 million units of electricity annually. The projects include the 12 MW Tankul, 120 MW Sirkari Bhyol-Rupsiyabagar and 72 MW\" \/>\n\t\t<meta name=\"twitter:image\" content=\"https:\/\/himalayanlive.in\/wp-content\/uploads\/2026\/11\/1280px-NSRS_Srisailam_Dam.jpg\" \/>\n\t\t<script type=\"application\/ld+json\" class=\"aioseo-schema\">\n\t\t\t{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"BlogPosting\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752#blogposting\",\"name\":\"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades - Himalayan Live\",\"headline\":\"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades\",\"author\":{\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?author=2#author\"},\"publisher\":{\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/#organization\"},\"image\":{\"@type\":\"ImageObject\",\"url\":\"https:\\\/\\\/himalayanlive.in\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/1280px-NSRS_Srisailam_Dam.jpg\",\"width\":1280,\"height\":960},\"datePublished\":\"2026-11-19T14:04:59+00:00\",\"dateModified\":\"2026-11-19T14:05:18+00:00\",\"inLanguage\":\"en-US\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752#webpage\"},\"isPartOf\":{\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752#webpage\"},\"articleSection\":\"Uttarakhand\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752#breadcrumblist\",\"itemListElement\":[{\"@type\":\"ListItem\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/#listItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/himalayanlive.in\\\/\",\"nextItem\":{\"@type\":\"ListItem\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?cat=4#listItem\",\"name\":\"Uttarakhand\"}},{\"@type\":\"ListItem\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?cat=4#listItem\",\"position\":2,\"name\":\"Uttarakhand\",\"item\":\"https:\\\/\\\/himalayanlive.in\\\/?cat=4\",\"nextItem\":{\"@type\":\"ListItem\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752#listItem\",\"name\":\"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades\"},\"previousItem\":{\"@type\":\"ListItem\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/#listItem\",\"name\":\"Home\"}},{\"@type\":\"ListItem\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752#listItem\",\"position\":3,\"name\":\"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades\",\"previousItem\":{\"@type\":\"ListItem\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?cat=4#listItem\",\"name\":\"Uttarakhand\"}}]},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/#organization\",\"name\":\"Himalayan Live\",\"url\":\"https:\\\/\\\/himalayanlive.in\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"url\":\"https:\\\/\\\/himalayanlive.in\\\/wp-content\\\/uploads\\\/2026\\\/08\\\/cropped-logo-top-1-scaled-1.png\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752\\\/#organizationLogo\",\"width\":2558,\"height\":749},\"image\":{\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752\\\/#organizationLogo\"}},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?author=2#author\",\"url\":\"https:\\\/\\\/himalayanlive.in\\\/?author=2\",\"name\":\"admin\",\"image\":{\"@type\":\"ImageObject\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752#authorImage\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/12061ad093f6230f14aedb4928a1be9f816b825e6f92e9c554b0b3689bfc3810?s=96&d=mm&r=g\",\"width\":96,\"height\":96,\"caption\":\"admin\"}},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752#webpage\",\"url\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752\",\"name\":\"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades - Himalayan Live\",\"description\":\"Dehradun: The way has been cleared for three long-pending hydropower projects in Uttarakhand, with a combined capacity of 204 MW. The projects, being developed by Uttarakhand Jal Vidyut Nigam Limited (UJVNL), are expected to generate 886.17 million units of electricity annually. The projects include the 12 MW Tankul, 120 MW Sirkari Bhyol-Rupsiyabagar and 72 MW\",\"inLanguage\":\"en-US\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/#website\"},\"breadcrumb\":{\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752#breadcrumblist\"},\"author\":{\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?author=2#author\"},\"creator\":{\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?author=2#author\"},\"image\":{\"@type\":\"ImageObject\",\"url\":\"https:\\\/\\\/himalayanlive.in\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/1280px-NSRS_Srisailam_Dam.jpg\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752\\\/#mainImage\",\"width\":1280,\"height\":960},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/?p=19752#mainImage\"},\"datePublished\":\"2026-11-19T14:04:59+00:00\",\"dateModified\":\"2026-11-19T14:05:18+00:00\"},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/#website\",\"url\":\"https:\\\/\\\/himalayanlive.in\\\/\",\"name\":\"Himalayan Live\",\"inLanguage\":\"en-US\",\"publisher\":{\"@id\":\"https:\\\/\\\/himalayanlive.in\\\/#organization\"}}]}\n\t\t<\/script>\n\t\t<!-- All in One SEO -->\n\n","aioseo_head_json":{"title":"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades - Himalayan Live","description":"Dehradun: The way has been cleared for three long-pending hydropower projects in Uttarakhand, with a combined capacity of 204 MW. The projects, being developed by Uttarakhand Jal Vidyut Nigam Limited (UJVNL), are expected to generate 886.17 million units of electricity annually. The projects include the 12 MW Tankul, 120 MW Sirkari Bhyol-Rupsiyabagar and 72 MW","canonical_url":"https:\/\/himalayanlive.in\/?p=19752","robots":"max-image-preview:large","keywords":"","webmasterTools":{"miscellaneous":""},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"BlogPosting","@id":"https:\/\/himalayanlive.in\/?p=19752#blogposting","name":"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades - Himalayan Live","headline":"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades","author":{"@id":"https:\/\/himalayanlive.in\/?author=2#author"},"publisher":{"@id":"https:\/\/himalayanlive.in\/#organization"},"image":{"@type":"ImageObject","url":"https:\/\/himalayanlive.in\/wp-content\/uploads\/2026\/11\/1280px-NSRS_Srisailam_Dam.jpg","width":1280,"height":960},"datePublished":"2026-11-19T14:04:59+00:00","dateModified":"2026-11-19T14:05:18+00:00","inLanguage":"en-US","mainEntityOfPage":{"@id":"https:\/\/himalayanlive.in\/?p=19752#webpage"},"isPartOf":{"@id":"https:\/\/himalayanlive.in\/?p=19752#webpage"},"articleSection":"Uttarakhand"},{"@type":"BreadcrumbList","@id":"https:\/\/himalayanlive.in\/?p=19752#breadcrumblist","itemListElement":[{"@type":"ListItem","@id":"https:\/\/himalayanlive.in\/#listItem","position":1,"name":"Home","item":"https:\/\/himalayanlive.in\/","nextItem":{"@type":"ListItem","@id":"https:\/\/himalayanlive.in\/?cat=4#listItem","name":"Uttarakhand"}},{"@type":"ListItem","@id":"https:\/\/himalayanlive.in\/?cat=4#listItem","position":2,"name":"Uttarakhand","item":"https:\/\/himalayanlive.in\/?cat=4","nextItem":{"@type":"ListItem","@id":"https:\/\/himalayanlive.in\/?p=19752#listItem","name":"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades"},"previousItem":{"@type":"ListItem","@id":"https:\/\/himalayanlive.in\/#listItem","name":"Home"}},{"@type":"ListItem","@id":"https:\/\/himalayanlive.in\/?p=19752#listItem","position":3,"name":"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades","previousItem":{"@type":"ListItem","@id":"https:\/\/himalayanlive.in\/?cat=4#listItem","name":"Uttarakhand"}}]},{"@type":"Organization","@id":"https:\/\/himalayanlive.in\/#organization","name":"Himalayan Live","url":"https:\/\/himalayanlive.in\/","logo":{"@type":"ImageObject","url":"https:\/\/himalayanlive.in\/wp-content\/uploads\/2026\/08\/cropped-logo-top-1-scaled-1.png","@id":"https:\/\/himalayanlive.in\/?p=19752\/#organizationLogo","width":2558,"height":749},"image":{"@id":"https:\/\/himalayanlive.in\/?p=19752\/#organizationLogo"}},{"@type":"Person","@id":"https:\/\/himalayanlive.in\/?author=2#author","url":"https:\/\/himalayanlive.in\/?author=2","name":"admin","image":{"@type":"ImageObject","@id":"https:\/\/himalayanlive.in\/?p=19752#authorImage","url":"https:\/\/secure.gravatar.com\/avatar\/12061ad093f6230f14aedb4928a1be9f816b825e6f92e9c554b0b3689bfc3810?s=96&d=mm&r=g","width":96,"height":96,"caption":"admin"}},{"@type":"WebPage","@id":"https:\/\/himalayanlive.in\/?p=19752#webpage","url":"https:\/\/himalayanlive.in\/?p=19752","name":"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades - Himalayan Live","description":"Dehradun: The way has been cleared for three long-pending hydropower projects in Uttarakhand, with a combined capacity of 204 MW. The projects, being developed by Uttarakhand Jal Vidyut Nigam Limited (UJVNL), are expected to generate 886.17 million units of electricity annually. The projects include the 12 MW Tankul, 120 MW Sirkari Bhyol-Rupsiyabagar and 72 MW","inLanguage":"en-US","isPartOf":{"@id":"https:\/\/himalayanlive.in\/#website"},"breadcrumb":{"@id":"https:\/\/himalayanlive.in\/?p=19752#breadcrumblist"},"author":{"@id":"https:\/\/himalayanlive.in\/?author=2#author"},"creator":{"@id":"https:\/\/himalayanlive.in\/?author=2#author"},"image":{"@type":"ImageObject","url":"https:\/\/himalayanlive.in\/wp-content\/uploads\/2026\/11\/1280px-NSRS_Srisailam_Dam.jpg","@id":"https:\/\/himalayanlive.in\/?p=19752\/#mainImage","width":1280,"height":960},"primaryImageOfPage":{"@id":"https:\/\/himalayanlive.in\/?p=19752#mainImage"},"datePublished":"2026-11-19T14:04:59+00:00","dateModified":"2026-11-19T14:05:18+00:00"},{"@type":"WebSite","@id":"https:\/\/himalayanlive.in\/#website","url":"https:\/\/himalayanlive.in\/","name":"Himalayan Live","inLanguage":"en-US","publisher":{"@id":"https:\/\/himalayanlive.in\/#organization"}}]},"og:locale":"en_US","og:site_name":"Himalayan Live -","og:type":"article","og:title":"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades - Himalayan Live","og:description":"Dehradun: The way has been cleared for three long-pending hydropower projects in Uttarakhand, with a combined capacity of 204 MW. The projects, being developed by Uttarakhand Jal Vidyut Nigam Limited (UJVNL), are expected to generate 886.17 million units of electricity annually. The projects include the 12 MW Tankul, 120 MW Sirkari Bhyol-Rupsiyabagar and 72 MW","og:url":"https:\/\/himalayanlive.in\/?p=19752","og:image":"https:\/\/himalayanlive.in\/wp-content\/uploads\/2026\/11\/1280px-NSRS_Srisailam_Dam.jpg","og:image:secure_url":"https:\/\/himalayanlive.in\/wp-content\/uploads\/2026\/11\/1280px-NSRS_Srisailam_Dam.jpg","og:image:width":1280,"og:image:height":960,"article:published_time":"2026-11-19T14:04:59+00:00","article:modified_time":"2026-11-19T14:05:18+00:00","twitter:card":"summary_large_image","twitter:title":"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades - Himalayan Live","twitter:description":"Dehradun: The way has been cleared for three long-pending hydropower projects in Uttarakhand, with a combined capacity of 204 MW. The projects, being developed by Uttarakhand Jal Vidyut Nigam Limited (UJVNL), are expected to generate 886.17 million units of electricity annually. The projects include the 12 MW Tankul, 120 MW Sirkari Bhyol-Rupsiyabagar and 72 MW","twitter:image":"https:\/\/himalayanlive.in\/wp-content\/uploads\/2026\/11\/1280px-NSRS_Srisailam_Dam.jpg"},"aioseo_meta_data":{"post_id":"19752","title":null,"description":null,"keywords":null,"keyphrases":{"focus":{"keyphrase":"","score":0,"analysis":{"keyphraseInTitle":{"score":0,"maxScore":9,"error":1}}},"additional":[]},"focus_keyword":null,"additional_keywords":null,"truseo_locale":null,"primary_term":null,"canonical_url":null,"og_title":null,"og_description":null,"og_object_type":"default","og_image_type":"default","og_image_custom_url":null,"og_image_custom_fields":null,"og_image_url":null,"og_image_width":null,"og_image_height":null,"og_video":"","og_custom_url":null,"og_article_section":null,"og_article_tags":null,"twitter_use_og":false,"twitter_card":"default","twitter_image_type":"default","twitter_image_custom_url":null,"twitter_image_custom_fields":null,"twitter_image_url":null,"twitter_title":null,"twitter_description":null,"schema_type":"default","schema_type_options":null,"schema":{"blockGraphs":[],"customGraphs":[],"default":{"data":{"Article":[],"Course":[],"Dataset":[],"FAQPage":[],"Movie":[],"Person":[],"Product":[],"ProductReview":[],"Car":[],"Recipe":[],"Service":[],"SoftwareApplication":[],"WebPage":[]},"graphName":"BlogPosting","isEnabled":true},"graphs":[]},"pillar_content":false,"robots_default":true,"robots_noindex":false,"robots_noarchive":false,"robots_nosnippet":false,"robots_nofollow":false,"robots_noimageindex":false,"robots_noodp":false,"robots_notranslate":false,"robots_max_snippet":"-1","robots_max_videopreview":"-1","robots_max_imagepreview":"large","priority":null,"frequency":"default","local_seo":null,"limit_modified_date":false,"ai":{"faqs":[],"keyPoints":[],"schemas":[],"titles":[],"descriptions":[],"socialPosts":{"email":{"subject":"","preview":"","content":""},"linkedin":[],"twitter":[],"facebook":[],"instagram":[]}},"breadcrumb_settings":null,"seo_analyzer_scan_date":null,"created":"2026-11-19 14:04:59","updated":"2026-11-19 15:15:19"},"aioseo_breadcrumb":"<div class=\"aioseo-breadcrumbs\"><span class=\"aioseo-breadcrumb\">\n\t\t\t<a href=\"https:\/\/himalayanlive.in\/\" title=\"Home\">Home<\/a>\n\t\t<\/span><span class=\"aioseo-breadcrumb-separator\">\u00bb<\/span><span class=\"aioseo-breadcrumb\">\n\t\t\t<a href=\"https:\/\/himalayanlive.in\/?cat=4\" title=\"Uttarakhand\">Uttarakhand<\/a>\n\t\t<\/span><span class=\"aioseo-breadcrumb-separator\">\u00bb<\/span><span class=\"aioseo-breadcrumb\">\n\t\t\tUttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades\n\t\t<\/span><\/div>","aioseo_breadcrumb_json":[{"label":"Home","link":"https:\/\/himalayanlive.in\/"},{"label":"Uttarakhand","link":"https:\/\/himalayanlive.in\/?cat=4"},{"label":"Uttarakhand Gets Forest Clearance for Three Hydropower Projects After Decades","link":"https:\/\/himalayanlive.in\/?p=19752"}],"_links":{"self":[{"href":"https:\/\/himalayanlive.in\/index.php?rest_route=\/wp\/v2\/posts\/19752","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/himalayanlive.in\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/himalayanlive.in\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/himalayanlive.in\/index.php?rest_route=\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/himalayanlive.in\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=19752"}],"version-history":[{"count":2,"href":"https:\/\/himalayanlive.in\/index.php?rest_route=\/wp\/v2\/posts\/19752\/revisions"}],"predecessor-version":[{"id":19755,"href":"https:\/\/himalayanlive.in\/index.php?rest_route=\/wp\/v2\/posts\/19752\/revisions\/19755"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/himalayanlive.in\/index.php?rest_route=\/wp\/v2\/media\/19753"}],"wp:attachment":[{"href":"https:\/\/himalayanlive.in\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=19752"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/himalayanlive.in\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=19752"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/himalayanlive.in\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=19752"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}